Track Record: Advisory Services

Name:
Delivery Risk Review 1

Project:  
Field Development

Client:
Major Oil & Gas Company



Description:

In developing a deepwater field off the coast of Nigeria, our client had chartered a deepwater drilling rig, which required extensive upgrading in Las Palmas before moving onto the drilling location. Èpeus were engaged to perform an independent assessment of when the rig would arrive on location following the upgrades.

To determine the most probable arrival date, Èpeus conducted a full review and quantitative risk analysis of the drilling contractor’s approach and management of the project. The review was conducted at the drilling contractor’s Houston offices. The Èpeus team forecast that the arrival date of the rig on location would in all probability be 5 weeks later than scheduled unless risk mitigation and contingency plans were implemented.

Risk mitigation and contingency plans were not implemented and our client adjusted its planning for mobilisation of client-supplied well construction equipment. The rig arrived on location 5 weeks later than the drilling contractors planning had identified but in line with the Èpeus forecast. 

In monetary terms, our client saved specialist equipment rental and third party costs on the order of an estimated US$5.25 Million by conducting the delivery risk review.

 

Name:
Delivery Risk Review 2

Project:  
Platform Upgrade

Client:
Major Oil & Gas Company



Description:

Our client planned to upgrade its drilling facilities on one of its platforms in the North Sea. Èpeus was engaged to assess the project so as to minimise downtime of the facilities.

 By conducting a qualitative risk review of the proposed project, Èpeus identified substantial opportunities to accelerate the work without compromising safety and bed space constraints. Our client exploited these opportunities, leading to completion of the project one week ahead of schedule and consequent resumption of normal platform activities ahead of expectations.

In value terms, our client realised 7 additional days production from the platform against their initial forecast.

 

Name:
Delivery Risk Review 3

Project:  
Platform Upgrade

Client:
Major Oil & Gas Company



Description:

Our client planned to conduct upgrades to one of its platforms on the UK Continental Shelf, North Sea, to enable the use Through Tubing Rotary Drilling (TTRD) methods. Èpeus was engaged to verity whether the project could be successfully completed within the proposed timescale of 101 days.

Èpeus conducted a qualitative and quantitative project risk review, which identified significant risks to an on-time completion, as well as technical issues impacting the schedule that had not been addressed by the FEED study. Èpeus developed risk mitigation and management plans that were implemented and resulted in an on-schedule delivery.

In value terms, the project would have overrun by a probable 25 days, thus disrupting production from the platform and impacting the revenue stream from the facility, if the review had not been conducted.

 

Name:
Delivery Risk Review 4

Project:  
Field Development

Client:
Major Oil & Gas Company



Description:

In developing a deepwater field offshore Angola, our client had chartered a deepwater drilling rig and had called for extensive upgrades to the drilling unit to be performed in Brazil prior to moving onto the drilling location. Èpeus was engaged to conduct an independent assessment of when the rig would arrive on location following the upgrades.

To determine the most probable arrival date, Èpeus conducted a full review and quantitative risk analysis of the drilling contractor’s approach and management of the project. The review was conducted at the drilling contractor’s Houston offices. The Èpeus team forecast that the arrival date of the rig on location would in all probability be 3 weeks later than scheduled unless risk mitigation and contingency plans were implemented.

Risk mitigation and contingency plans were not implemented and our client adjusted its planning for mobilisation of client supplied well construction equipment. The rig arrived on location 3 weeks later than the drilling contractors planning had identified but in line with the Èpeus forecast. 

In monetary terms, our client saved specialist equipment rental and third party costs on the order of an estimated US$2 Million by conducting the Delivery Risk Review.

 

Name:
Delivery Risk Review 5

Project:  
Platform Construction

Client:
Major Oil & Gas Company



Description:

In connection with development of a field west of the Shetlands on the UK Continental Shelf, the proposed production platform facilities included a 5th-generation drilling rig. The project schedule had extended, and our client sought an independent assessment of when “first oil” could be produced from the platform.

Because the critical path for the project was the commissioning of drilling facilities, Èpeus was engaged to conduct an evaluation of the project with particular attention to the strategy and approach to the drilling facilities commissioning. The Èpeus team forecast that “first oil” would be produced 3 months later than planned unless mitigation and management of the risks was implemented.

Our client decided not to implement the recommended mitigation and management plans. The actual “first oil” announcement date was 3 months later than planned and in line with the Èpeus team’s forecast.  The platform was to produce approximately 50,000 barrels per day. The delay cost our client and its partner substantial lost revenue plus extended project costs.

 

Name:
Feasibility Investigation 1

Project:  
Platform Upgrade

Client:
Major Oil & Gas Company



Description:

Our client planned an upgrade project after a recent purchase the of a production platform.  Part of the planned upgrades included modernising the drilling facilities to allow extended reach directional drilling operations.

After our client’s platform drilling contractor had performed their conceptual design studies, Èpeus was engaged to conduct an independent investigation into feasibility, costing, and potential consequences of the project. The Èpeus team found that the project as proposed was significantly larger and more complex than would be required to achieve the client’s objectives.

 In percentage terms, our client had the opportunity to reduce the overall cost of the project by an estimated 20% against an initial proposed project cost on order of magnitude of US$100 Million.

 

Name:
Feasibility Investigation 2

Project:  
Platform Upgrade

Client:
Major Oil & Gas Company



Description:

Prior to starting a new drilling program, our client planned to upgrade and modernise the drilling facilities on the one of its platforms in an effort to eliminate historical equipment downtime.

After the platform drilling contractor finished its project definition studies, Èpeus was engaged for input on the project and to perform an independent investigation to evaluate whether the proposed upgrades would add the expected value to drilling operations.  Èpeus performed a number of investigations, technical evaluations, and cost benefit analyses to ascertain the probability of meeting our client’s objectives successfully.

The value benefit to the client was:

  • Independent specialist input that the client could not provide in house.

  • Peace of mind that issues were being rigorously investigated and challenged.

  • No additional in house management expense.

Name:
Feasibility Investigation 3

Project:  
Under Balanced Drilling

Client:
Major Oil & Gas Company



Description:

Our client was considering whether to undertake an under balanced drilling program using crude oil as the drilling fluid. After the platform drilling contractor finished their project definition studies,

Èpeus was engaged during the project concept phase for input and to perform an independent investigation regarding whether the proposed upgrades would meet the technical, safety, environmental, and operational parameters of the client. Èpeus performed a number of investigations, technical evaluations, and cost benefit analyses to ascertain the probability of successfully meeting our client’s objectives.

The value benefit to the client was:

  • Independent specialist input that the client could not provide in house.

  • Peace of mind that issues were being rigorously investigated and challenged.

  • No additional in house management expense.

Name:
Risk Profiling 1

Project:  
Field Development

Client:
Major Oil & Gas Company

Description:

In developing one of its fields in the central North Sea, our client had engaged a drilling contractor to drill high-pressure, high-temperature wells. Èpeus was engaged to model the risks and costs of using semisubmersibles, jack-ups, and other specialist vessels for various well completion options and extended well testing, as well as subsea tiebacks for early production.

The value benefit to the client was:

  • Independent specialist input that the client could not provide in house.

  •  Peace of mind that issues were being rigorously investigated.

  •  No additional in-house management expense.

  • A quantitative completions risk model that could be updated and interrogated over the life of the project.

  • Clear and concise information for decision making early on the project.

Name:
Knowledge Capture
& Transfer 1

Project:  
Platform Construction

Client:
Major Oil & Gas Company

Description:

Our client had determined that development of the its field in the Caspian Sea required construction and installation of 4 production platforms, each of which would be fitted with 5th-generation automated drilling facilities. Our client had experienced significant cost increases in construction and commissioning of the drilling facilities.

Èpeus was engaged during execution of the construction projects to conduct independent project audits on its project teams and key contractors. We were also engaged to provide a baseline from which adjustments could be made to the initial approach to reduce the cost overruns.

Èpeus performed an independent “lessons learned” review of the early and ongoing construction strategy and approach. The outcomes were a significant reduction in costs moving forward and delivery of the last set drilling facilities on budget and on time.

The value benefit to the client was:

  • Independent capture and evaluation of what went well and not so well.

  • Minimal impact to ongoing work.

  •  Not having to temporarily shift the focus of internal project resources.

  • Access to an established support organisation and knowledge base.

  • Knowledge Transfer from other similar projects.

In monetary terms it is estimated that our client saved in the order of $70 million USD by adjusting their approach to the projects relative to the ongoing situation.

 

Name:
Knowledge Capture
& Transfer 2

Project:  
Field Development

Client:
Major Oil & Gas Company

Description:

In developing a deepwater field offshore Angola, our client had chartered a deepwater drilling unit and had called for extensive upgrades to the drilling unit to be performed in Brazil prior to moving onto the drilling location.

Èpeus was engaged early in the process for a Delivery Risk Review (outlined elsewhere), as well as on-going monitoring and performance audits. During the latter stage of the project, we were engaged to capture the lessons learned relative to the earlier Delivery Risk Review.

The “lessons learned” review revealed that most of the risks identified in the Delivery Risk Review had negatively affected the progress of the upgrade project by collectively causing an avoidable 3 week delay in the Brazilian shipyard despite acceleration efforts by the drilling contractor. The Knowledge Capture and Transfer process enabled our client to better understand the risk profile of drilling rig upgrades so that it could adjust their overall field development planning.

The value benefit to the client was:

  •  Independent capture and evaluation of what went well and not so well.

  •  Minimal impact to ongoing work.

  • Not having to temporarily shift the focus of internal project resources.

  • Access to an established support organisation and knowledge base.

Name:
Project Manual Development

Project:  
Various

Client:
Major EPC

Description:

Our client had identified one of their divisions that needed a better management and control system for its projects.

Èpeus was engaged, which developed the Divisional Project Manual to describe how to manage and control projects.

The value benefits to the client were:

  • Not having to temporarily shift the focus of internal divisional project resources.

  •  Access to an established support organisation and knowledge base.

  • Knowledge Transfer from other similar approaches.

  • Accelerated delivery of the manual relative to an in house approach.

Name:
Dispute Resolution 1

Project:  
Drill Rig Construction

Client:
Major Drilling Contractor

Description:

Our client commissioned the construction of a series of ultra-deepwater drill ships.  After integration of the topsides with the hulls on both vessels, the main contractor made a project escalation claim. 

Èpeus provided project knowledge, deposition testimony, and expert witness services during the pre-trial phase of litigation. The dispute was settled out of court for substantially less than the total claimed by the construction contractor.

The value benefits to the client were:

  • Not having to temporarily shift the focus of internal resources.

  •  Access to an established support organisation and knowledge base.

  •  Knowledge Transfer from other similar cases.

  • Satisfactory outcome of the case.

   

 
 
 
 
Terms Of Use | Site Map

© Èpeus Group 2009. All rights reserved.