Project Background
Client : A drilling contractor
Project : FEED study looking at
certain Through Tubing Rotary Drilling (TTRD) upgrades
to platform drilling facilities.
Situation : Competitive tendering
for the Project Management and Engineering for an
estimated project duration of 101 days.
Èpeus was asked to conduct a review
of the project and verify whether the project could be
successfully implemented within the proposed timescale
of 101 days.
The Findings
The review revealed that significant
risks to completion within schedule existed and also
identified that certain technical issues had not been
addressed by the FEED study. The project model placed a
10% probability (P10) of successful completion
indicating that the contractor was optimistic when
setting schedule milestones. Risk mitigation exercises
were conducted resulting in a re-schedule of the
project. This time the output reflected a 90% (P90)
probability providing that the new project strategy was
implemented.
Project Outcome
Graphical outputs from the model
were included in the tender to demonstrate independent
verification of their proposed strategy and schedule.
Although the contractor was not the lowest bidder they
were awarded the work. Èdge Enhancer has been designed
specifically to provide you with an edge over the
competition by demonstrating your ability to deliver.
|
|
| |
|